Piling removal cost escalates as Norfolk light rail project continues
04:09 PM EST on Friday, January 23, 2009
NORFOLK – Light rail has another financial derailment to deal with.
Sky13
These are some of the 260 wooden pilings that are being removed from Broad Creek.
Hampton Roads Transit officials contracted to remove 20 old wooden pilings from Broad Creek to build a new concrete bridge. When low tide arrived, crews found 260 pilings, not just 20.
Removing the others will cost HRT an additional $369,200.00.
According to 13News’ partners at the Virginian Pilot, the cost of the 7.4-mile rail line has grown to $288 million from $232.1 million just more than a year ago when construction began.
The Tide’s opening date has been pushed from early 2010 to at least mid-2010.
More Top Stories
Today's Most Read Stories
Dominion Virginia Power to return $400M, trim rates
Hijackers have success on social networking sites
Forums, Photos & More
Explore: Find Web sites making news in our Links in the News section.
Keep Up: Have 13News headlines delivered to your RSS reader.
Tell us: Is there something you believe 13NEWS should investigate? Please let us know.
Popular Stories





You must be logged in to contribute. Log in | Register Now!
You are logged in as screenname | Log Out
You are logged in, but do not have a "screen" name. Create a Screen Name